The real benefit of the earned value method is in the early warning signal it provides. In my previous life at a large engineering company, I saw many project managers get to a monthly billing cycle before they realized the project was behind, and even then they would rationalize it by deciding their project team was going to be more efficient in the next cycle. Suffice to say that didn’t usually happen. But this behavior is not project management. It’s passive, reactive, and virtually assures that projects finish behind and over budget.
On the flip side, project managers who understand and use the earned value management system are better equipped to finish their projects on time and budget, which helps their careers and salary prospects immensely.
In this article I will show you how ACWP is used in the earned value method, and finish with an example.
ACWP
Actual Cost of Work Performed, usually abbreviated as ACWP, is one of the fundamental inputs of the Earned Value Management System. It is defined by the Project Management Institute as:
- The realized cost incurred for the work performed during a specific time period.
It is one of 3 pieces of data that the project manager collects before applying the earned value formulas to determine the project’s schedule and budget status. The other two are:
- Budgeted Cost of Work Scheduled (BCWS): The authorized, time-phased budget assigned to accomplish the scheduled work.
- Budgeted Cost of Work Performed (BCWP): The measure of work performed at a specific point in time, expressed in terms of the approved budget authorized for that work.
A fourth value, the Budget at Completion (BAC) completes the list of inputs but it does not require any extra work to collect. It is simply the project’s overall budget.
Background
ACWP is not rocket science. It is simply the cost of the work to date.
Most organizations have systems in place to track the project’s actual cost. The bigger issue is often how up to date the information is, and the project manager must go around and make sure the project team has entered all their time and expenses before performing the earned value calculation.
ACWP must include all of the items of expense that were necessary to complete the project, such as:
- Labor
- Materials
- Equipment & Tools
- Intangibles
- Subcontractors
Sometimes there are items that include a grey area, such as when a member of the project team purchases tools that will be used by a department once the project is done. Does the department manager cover some of the cost? If so, how much? Unfortunately there is no magic formula for this. These types of questions simply need to be answered because the project has a fixed budget that has not been designed to absorb extra items.
In a normal application of the earned value method, the ACWP must be calculated on a task by task basis and summed to produce the project’s ACWP.
Many tasks are not completed in a linear fashion. For example, in the task called “Set Up Database” the task might require 1 person for the first half and 4 people for the last half. This results in the cost of the task being mostly incurred at the tail end, and skews the earned value results if you use a linear percent complete.
Most tasks should be small enough that this is not a major issue. But if you have a large expense all at once, like a subcontractor payment, you can adjust the Budgeted Cost of Work Planned (BCWP) by the same amount to avoid misleading negative cost or schedule variances.
Interpretation
Let’s take an example project task. The budget and schedule baseline, which are developed during the project planning phase, are:
ID | Name | Budget | Start | End |
---|---|---|---|---|
100 | Set up Database | $10,000 | Mar. 1 | Mar. 10 |
When the earned value analysis is performed, the project manager determines BCWP, BCWS, and ACWP for the task. Let’s say it’s March 5, the task is 40% complete, and the actual cost of the task is $3,000.
- BCWS is $5,000. The task should be half complete.
- BCWP is $4,000. The task is actually less than half complete.
- ACWP is $3,000. The task has spent less than it has been scheduled to at this point.
The basic earned value formulas fall into two categories – Cost and Schedule. The Cost status of the project is:
- Cost Variance: CV = BCWP – ACWP = $1,000. Because this is positive, the project is under budget.
- Cost Performance Index: CPI = BCWP / ACWP = 1.33. This means the project has spent 33% less than it should have at this point in time.
The schedule status is:
- Schedule Variance: SV = BCWP – BCWS = -$1,000. Because this is negative, the project is behind schedule.
- Schedule Performance Index: SPI = BCWP / BCWS = 0.80. This means the project is performed 80% of the work it should have at this point in time.
Related Earned Value Metrics
The other inputs to the earned value method are as follows:
- Budgeted Cost of Work Scheduled (BCWS): Also known as Planned Value (PV), this is the amount that the task should have been completed at the point of analysis (usually today).
BCWS = % Complete (Planned) x Task Budget
For example, if the task budget is $10,000, the task dates are from March 1 to March 10 and it’s March 5 today, BCWS = 50% x $10,000 = $5,000.
- Budgeted Cost of Work Performed (BCWP): Also known as Earned Value (EV), this is the amount of the task that is actually completed. It is calculated from the project budget.
BCWP = % Complete (Actual) x Task Budget
For example, if the actual percent complete is 75% and the task budget is $10,000, BCWP = 75% x $10,000 = $7,500.
Earned Value Example
This example will walk you through a basic earned value calculation for a hypothetical project with two tasks.
Before we start, the baseline developed during project planning is:
ID | Task | Start date | End Date | Budget |
---|---|---|---|---|
100 | Set up Database | Mar. 1 | Mar. 10 | $10,000 |
200 | Enter Data | Mar. 5 | Mar. 15 | $30,000 |
TOTAL | $40,000 |
Let’s say it’s Mar. 11. Determine the BCWS, BCWP, and ACWP for the Project.
Step 1: Determine Budgeted Cost of Work Schedule (BCWS)
- Task 100 should be complete. BCWS = $10,000.
- Task 200 should be 60% complete, because it’s Mar. 11 and the task goes from Mar. 5 to Mar. 15. Therefore, BCWS = 60% x $30,000 = $18,000.
We will add a column called ‘BCWS’ to the table.
ID | Task | Start date | End Date | Budget | BCWS |
---|---|---|---|---|---|
100 | Set up Database | Mar. 1 | Mar. 10 | $10,000 | $10,000 |
200 | Enter Data | Mar. 5 | Mar. 20 | $30,000 | $18,000 |
TOTAL | $40,000 | $28,000 |
Step 2: Determine Budgeted Cost of Work Performed (BCWP)
Please note, the determination of BCWS, above, is derived from the Percent Complete (Planned), which is different than Percent Complete (Actual). Since this is not a real project we will have to make an assumption for Percent Complete (Actual). Let’s say the tasks are 75% and 50% complete, respectively.
- Task 100 is 75% complete, therefore BCWP = 75% x $10,000 = $7,500.
- Task 200 is 50% complete, therefore BCWP = 50% x $30,000 = $15,000.
Next we will add a column called BCWP.
ID | Task | Start date | End Date | Budget | BCWS | BCWP |
---|---|---|---|---|---|---|
100 | Set up Database | Mar. 1 | Mar. 10 | $10,000 | $10,000 | $7,500 |
200 | Enter Data | Mar. 5 | Mar. 20 | $30,000 | $18,000 | $15,000 |
TOTAL | $40,000 | $28,000 | $22,500 |
Step 3: Determine Actual Cost of Work Performed (ACWP)
Since this is a fictional project we will have to make another assumption.
- Task 100’s actual cost is $12,000.
- Task 200’s actual cost is $13,000.
Next we will add a column called ACWP.
ID | Task | Start date | End Date | Budget | BCWS | BCWP | ACWP |
---|---|---|---|---|---|---|---|
100 | Set up Database | Mar. 1 | Mar. 10 | $10,000 | $10,000 | $7,500 | $12,000 |
200 | Enter Data | Mar. 5 | Mar. 20 | $30,000 | $18,000 | $15,000 | $13,000 |
TOTAL | $40,000 | $28,000 | $22,500 | $25,000 |
Step 4: Determine Schedule Variance (SV) and Schedule Performance Index (SPI)
SV = EV – PV.
SPI = EV / PV.
ID | Task | Start date | End Date | Budget | BCWS | BCWP | ACWP | SV | SPI |
---|---|---|---|---|---|---|---|---|---|
100 | Set up Database | Mar. 1 | Mar. 10 | $10,000 | $10,000 | $7,500 | $12,000 | -$2,500 | 0.75 |
200 | Enter Data | Mar. 5 | Mar. 20 | $30,000 | $18,000 | $15,000 | $13,000 | -$3,000 | 0.83 |
TOTAL | $40,000 | $28,000 | $22,500 | $25,000 | -$5,500 | 0.81 |
The project is behind schedule because SV is negative. Both tasks are behind schedule because their SV’s are negative. The project is behind schedule by $5,500 (out of the total project $40,000) which seems significant, and the SPI of 0.81 says that the project should have accomplished 19% more than it actually has at this point. Clearly this project manager has work to do if this project is to finish on time.
Step 5: Determine Cost Variance (CV) and Cost Performance Index (CPI)
CV = EV – AC.
CPI = EV / AC.
ID | Task | Start date | End Date | Budget | BCWS | BCWP | ACWP | CV | CPI |
---|---|---|---|---|---|---|---|---|---|
100 | Set up Database | Mar. 1 | Mar. 10 | $10,000 | $10,000 | $7,500 | $12,000 | -$4,500 | 0.63 |
200 | Enter Data | Mar. 5 | Mar. 20 | $30,000 | $18,000 | $15,000 | $13,000 | $2,000 | 1.15 |
TOTAL | $40,000 | $28,000 | $22,500 | $25,000 | -$2,500 | 0.90 |
On the cost side, one task is over budget and one is under budget. But the total CV is negative therefore the project is over budget. The CPI of 0.90 means the project has spent 10% more than it should have at this point.
Although the project has both cost and schedule problems, the cost problems are not nearly as significant.
Leave a Reply