Because you can’t see its results in a direct way, project risk analysis is too often sacrificed by project managers in the name of time or budget constraints. Compounding the problem is that small projects just don’t seem to have the time and budget to justify the time spent on risk management. But I would argue that if risk management is a priority on megaprojects it would have a corresponding positive effect on small projects.
Actually, megaprojects have entire teams devoted to risk management, and PMI’s RMP certification recognizes an entire profession around it.
On small projects, in fact, risk analysis can often be spread throughout many similar projects which incur the same risks, thereby reducing the cost of risk management activities per project. For example, a plumbing firm could have a risk register for a commercial building project, a residential building, a hot water tank repair project, etc.
The risk management process looks like this:
- Risk Identification
- Risk Analysis
- Qualitative Analysis
- Quantitative Analysis
- Develop Risk Response Plans
During the initial Risk Identification step (step 1), a risk register iss completed which is simply a list of the most important risks to the project. For example, the initial risk register might look like this:
Risk Register | |
---|---|
ID | Description |
1 | Haul truck breaks down |
2 | Weather makes haul road impassable |
3 | Truck drivers call in sick |
4 | Airplane crashes into haul road |
In this second step, the risks will be prioritized by their underlying factors, probability and impact. More specifically, the following columns will be added:
- Probability
- Impact
- Priority
From those, the highest priority risks will be identified for the third step, which is risk response planning.
It is okay, even recommended, that the original list have some risks that are determined insignificant and will be struck off. The focus during the first step was on ensuring nothing was missed. In our example we will strike off risk #4, because it is immediately deemed too unlikely to happen.
Risk Register | |
---|---|
ID | Description |
1 | Haul truck breaks down |
2 | Weather makes haul road impassable |
3 | Truck drivers call in sick |
We then proceed to the meat and potatoes of the risk analysis. Risk analysis has two components:
- Qualitative Risk Analysis
- Quantitative Risk Analysis
Qualitative Risk Analysis
In the qualitative risk analysis phase, a probability and an impact score is given to each risk. Since risk has two components, probability and impact, both need to be considered.
Risk = Probability x Impact
Probability
Assessing the probability of an uncertain event is a difficult task. In the insurance industry, actuaries use similar events with known statistical outcomes to determine a standard “distribution” for an unknown event. Here are some ideas to determine the probability of an event happening:
- Determine how often the event actually occurred on previous projects. Many projects have tasks that have been performed on other projects. For example, if an event occurred twice in ten previous projects, the probability of the event might be approximately 20%.
- Compare to a known probability. The odds of throwing a dice and landing on a six are obviously 6:1. The odds of giving birth to twins is 70:1. Maybe you have a known probability of an event within your company or project. Compare your uncertain outcome to something certain.
- Decompose the risk into constituent parts. Are there any sub-events that contain a known probability, which can then result in a better estimation of the whole?
- Ask experts to rank the risks as “high/medium/low.” Then average the answers into a score out of 10. Using broad categories to assign probabilities makes it clear which one the event belongs in, then averaging the result into a greater distribution utilizes the wisdom of crowds.
Probability can be stated in a percentage or return period (eg. 6:1). For small projects I suggest using a simple 1-10 scale.
Our example risk register now looks like this:
Risk Register | ||
---|---|---|
ID | Description | Probability |
1 | Haul truck breaks down | 7 |
2 | Weather makes haul road impassable | 8 |
3 | Truck drivers call in sick | 3 |
Impact
The impact of the event is often easier to define but can be a range of possibilities rather than an exact number. There are many different aspects of the project which can be impacted, but the most common are:
- Cost
- Schedule
- Quality (technical performance)
Impact can be stated in monetary terms (i.e. dollar, euro, etc.). However, for small projects I would recommend simply using an empirical scale of 1-10. Since this is a small project, we’ll use the 1-10 scale. Our example risk register now looks like this:
Risk Register | |||
---|---|---|---|
ID | Description | Probability | Impact |
1 | Haul truck breaks down | 7 | 9 |
2 | Weather makes haul road impassable | 8 | 9 |
3 | Truck drivers call in sick | 3 | 7 |
Risks #1 and #2 will shut down the operation but risk #4 could result in partial success, hence the lower impact score.
Priority
The purpose of risk analysis is to determine the overall priority of a risk so that further action can be taken appropriately. There are two primary ways to amalgamate the probability and impact into an overall priority:
- If you’ve stated the probability in percent (or return period) and the impact in monetary terms (dollars, etc.), you can simply multiply them to obtain the risk level. This value essentially functions as a contingency. If you performed the exact same project many times, this amount would be the ideal contingency.
- If you’ve simply ranked or prioritized each risk on a scale of 1-10 (or similar) you can multiply the values to obtain a priority level. This number will not have any meaning outside of individually ranking the risks.
In our example, since we used 1-10 rankings for both we can simply multiply them to get a priority:
Risk Register | |||||
---|---|---|---|---|---|
ID | Description | Probability | Impact | Score | Priority |
1 | Haul truck breaks down | 7 | 9 | 63 | 2 |
2 | Weather makes haul road impassable | 8 | 9 | 72 | 1 |
3 | Truck drivers call in sick | 3 | 7 | 21 | 3 |
Based on this analysis the weather (risk #2) should be the highest priority. If the probability and impact are considered severe enough you might proceed to step 3, the preparation of risk response plans, for this risk and any other risk for which it is deemed appropriate.
Based on the priority of the list, the bottom risks can be removed altogether or added to a “watch list.” The watch list could be monitored throughout the project to ensure they do not increase in probability and/or impact to the point of requiring response plans or other action.
Quantitative Risk Analysis
The second component of risk analysis consists of turning the probabilities and impacts into quantifiable project budget impacts. This is done via simulations such as Monte Carlo analysis and generally requires project management software. Unlike the qualitative analysis, the probabilities must be in percent form and the impacts in monetary (i.e. dollar, euro) form.
In the simplest of quantitative risk analyses, a probability and impact can be multiplied into a risk score. This is effectively a contingency that the project should account for.
Risk Register | ||||
---|---|---|---|---|
ID | Description | Probability | Impact | Risk Score |
1 | Haul truck breaks down | 10% | $50,000 | $5,000 |
2 | Weather makes haul road impassable | 20% | $50,000 | $10,000 |
3 | Truck drivers call in sick | 2% | $20,000 | $400 |
In a Monte Carlo analysis, the risks are simulated by assigning a distribution curve to each risk and then running the simulation many times to determine the cost contingencies that should be built into the project budget. The two main variables, probability and impact, are given a distribution (normal distribution, beta distribution, etc.). Then, a random result is picked from the distribution to simulate the occurrence of the risk. The actual cost to the project by the event is calculated, and the test is run many times which results in a distribution curve of the project’s actual budget. Thus, it gives you a probability range of actual costs for the project, which is great for management presentations. However, like any analysis it’s garbage in, garbage out, and the confidence level of the results are never better than the distribution of the initial risks, often an educated guess at best.
The Risk Management Plan
The risk register and risk response plans are rolled up into and become the main part of the risk management plan, which is a component of the overall project management plan.
In practical terms, the risk management plan can be a stand alone document or a section of the project management plan but it still serves as a sub-section of the project management plan.
The rest of the risk management plan contains things like:
- More detailed description of risks
- Discussion of risks
- Definitions of probability and impact scores, for example 1-3 means ‘not likely to occur’
Good luck with your risk analysis. Let me know if you have any questions or anything to add.
khalsa says
April 24, 2018 at 1:05 pmi want to help to resolve this
telematics PLC is considering two mutually project Cables and Satelite . the possible NPVs for reach project and thier associated probabilities are as follows :-
cable
NPV Probability of occurrence
10 0.1
20 0.5
25 0.4
Satellite
NPV Probability of occurrence
15 0.6
20 0.2
40 0.2
calculate Expected NPVs and calculate Standard Deviation
Christiana mensah says
August 19, 2019 at 4:22 pmWell explained, I was struggling with my project. Thank you. Will also need help with how to plan a response according to priority, risk assessment with risk description, severity, response, contingence,risk trigger and responsible person and how to monitor and control risk