Top Down estimating is a project estimating technique whereby the overall project is estimated first, and individual tasks are apportioned from it. You start from the top of the pyramid and work downwards.
This type of project budgeting usually occurs when there is a fixed budget and/or the scope of the project must fit within a predetermined funding level, particularly when projects aren’t blessed with the resources of King Tut’s afterlife.
Top Down is the opposite of Bottom Up Estimating, whereby individual tasks are estimated first and “rolled up” into the overall project estimate.
Accuracy
In top down estimating, individual task estimates are only as accurate as the overall project estimate they are derived from. If the overall estimate is incorrect, nothing, except for maybe sacrifices to the sun god Ra, will make the individual task estimates any more accurate. And because projects are normally tracked via individual tasks, this could lead to issues during the project when individual tasks are incorrectly apportioned, even though the overall estimate is correct. This introduces an additional level of risk over Bottom Up Estimating, and you’d be surprised how quickly the mummies come out of their tombs when project estimates are inaccurate.
Cost Estimating
In the Project Management Body of Knowledge (PMBOK), there are three estimating levels which are used for individual tasks:
- Analogous Estimating is the determination of an estimate based on previous, similar projects, for example, the neighbor’s fence cost $10,000 therefore ours should cost $12,000.
- Parametric Estimating involves the use of a unit cost times a number of units. The unit cost can come from previous projects, or from industry-wide published data. For example, the neighbor’s fence cost $10/foot.
- Three Point Estimating. This method involves the determination of an optimistic, pessimistic, and most likely estimate. The final estimated value can be derived using either the triangular distribution:
E = (a + m + b) / 3
or the beta distribution:
E = (a + 4m + b) / 6
- E = Final estimated cost
- a = Optimistic estimate
- m = Most Likely estimate
- b = Pessimistic estimate
It may seem like hieroglyphs, but three point estimating is a powerful method that takes into account project risks, and can be used in conjunction with the other two.
These methods apply to individual tasks and are part of the PMBOK’s Estimate Costs process. Once each task is estimated, the overall project budget is determined using the Determine Budget process.
The Overall Project Budget
The Determine Budget process contains the procedures to roll up the individual task estimates into an overall project budget. Top Down Estimating is one of two procedures for this process. The other one is:
- Bottom Up Estimating is the determination of individual task estimates first, followed by rolling up the task estimates into an overall project estimate.
Bottom Up Estimating is more common, because Top Down is largely restricted to situations where a budget has been determined in advance and the project manager must determine the project scope that fits the budget.
In conclusion, keep the mummies in their tombs by using top down estimating to determine project level estimates first and then apportioning it down to the individual task level estimates.
THOMAS NAGAPURATHU CHACKO says
November 13, 2018 at 10:13 pmI’m trying find out what category parametric estimating and three-point estimating belongs to. Are they top-down or bottom-up estimating?